Sprint Goal / Focus 

  • Bugfest 

Sprint Schedule

  • Sprint: 161
  • Release: 2023.1 Orchid  
    • Sprint 162: Bugfix Release Deadline (31 Mar 2023) [FOLREL-581]
  • Release: 2023.2 Poppy  
    • Sprint 3 of 8 since Release Development Cycle Starts (Sprint 159) to Feature Freeze (Sprint 166)
    • Sprint 168: Module Release Deadline (16 Jun 2023) [FOLREL-565]
    • Sprint 170: Bugfix Release Deadline (21 Jul 2023) [FOLREL-581]

Development Meetings

  • 15 Mar
  • 20 (Mid Sprint Review)
  • 22 Mar

Sprint Capacity

Team AvailabilitySchedule | Calendar

Notes / Exceptions:

  • NA

Lead Roles:

QA Environment: 

  • folio-snapshot, folio-snapshot-2

Present

Planning Questions

  • Does the issue meet the criteria for Definition of Ready?
  • What front and back end components are affected?
  • What changes need to be made? (additions, removals or modifications)
  • What development tests need to be written?  
  • What data does the developer need to verify their work?
  • What are the known unknowns? 
  • What is needed to QA? (environment, data, scripts)

Navigation

  1. Sprint Goal / Focus
  2. Sprint Capacity
  3. Review sprint candidates 
  4. Agree technical approach / define key implementation tasks
  5. Finalise estimates / costings
  6. Confirm sprint scope
  7. Confirm first actions





Sprint Planning  

(error) - not in sprint

(tick) or @ - in sprint 

(warning) - not ready

(question) - pending triage / planning


Sprint Focus


Planning Notes Template

  • Triage

  • Approach
  • Components and Changes

    • Frontend

    • Backend

  • Tests / Data / Dependencies

  • Known Unknowns

  • QA: snapshot | local | testing | other

  • Release Target: 
  • Development Estimate

UXPROD-3861 - Getting issue details... STATUS

Issue ID

Sprint Backlog?

Notes / Estimates / Actions

ERM-1026 - Getting issue details... STATUS

(question)

ERM-1061 - Getting issue details... STATUS

(question)

ERM-1795 - Getting issue details... STATUS

(question)

ERM-2064 - Getting issue details... STATUS

(tick)

  • Triage

    • Not showing all the applicable validation messages
      • Potentially increase the drag and drop file upload space to accommodate
    • Currently: 
      • If upload error, could be displaying 3 messages
      • final form and validator behaviour clashes resulting in erroneous error behaviour
  • Approach
    • Move drop validation to toast message (to eliminate state-based error display)
    • Move logic to toast notification (callout rather than field validation)
  • Components and Changes

    • Frontend

    • Backend: none

  • Tests / Data / Dependencies / Known Unknowns: none

  • QA: snapshot 

  • Release Target: Poppy
  • Development Estimate 

Tests

Issue ID

Sprint Backlog?

Notes / Estimates / Actions

ERM-2773 - Getting issue details... STATUS

(error)

ERM-2812 - Getting issue details... STATUS

(error)


Release Tasks (Orchid Bugfix)

Backend: 1d

Frontend: 2d

Issue ID

Sprint Backlog?

Notes / Estimates / Actions

ERM-2640 - Getting issue details... STATUS



ERM-2648 - Getting issue details... STATUS



ERM-2649 - Getting issue details... STATUS



Release Tasks (Non-Flower Release)

Issue ID

Sprint Backlog?

Notes / Estimates / Actions

NA



Maintenance

Issue ID

Sprint Backlog?

Notes / Estimates / Actions

NA



Changes

(plus) Added

(minus) Removed: note whether rescheduled or deferred

Feature ID

Issue ID

Change

Notes


ERM-2883 - Getting issue details... STATUS





Rolled Over From Previous Sprint


Planning Notes Template

  • Current State
  • TODO
  • Development Estimate

In Development

Feature ID

Issue IDSprint Backlog?

Notes / Estimates / Actions


ERM-2633 - Getting issue details... STATUS

ERM-2624 - Getting issue details... STATUS

ERM-2625 - Getting issue details... STATUS

  • Current State
    • In Code Review
  • TODO
  • Development Estimate

ERM-2612 - Getting issue details... STATUS

  • Current State
    • In Code Review
  • TODO
  • Development Estimate

ERM-2643 - Getting issue details... STATUS

  • Current State
    • In Code Review
    • Rhino removed
  • TODO
  • Development Estimate

ERM-2630 - Getting issue details... STATUS

  • Current State
    • Unlikely to be parallelised at this point
    • Confidence in how it will act in production service
    • Verified that can remove Remote KBs from domain model
    • Package ingest almost done
  • TODO
    • Finish package ingest from endpoint: make sure it can save to db
    • Issues to address around pushKB service
      • Separate (non-blocker) to package ingest development
    • Tweak title ingest and schema 
    • Refactor title and package ingest services
      • to ensure correctly attaching from outside package
    • Write external pushKb service (ERM-2631)
      • Unknown: how will a developer service work around this for debugging and developing?
      • May need enabling tooling to support development workflow
  • Development Estimate: 2 sprints


Sprint Backlog

Feature IDIssue IDSprint Backlog?

Notes / Estimates / Actions









Blocked

Feature IDIssue IDSprint Backlog?

Notes / Estimates / Actions


ERM-2645 - Getting issue details... STATUS

Claudia Malzer 
  • Current State
    • Blocked
    • Want to avoid re-writing these by avoiding using the interactors (resulting in extra redundant patterns)
  • TODO
    • Needs conversation between Bienenvolk, AQA and Stripes Testing team to support reusable test data for unit and e2e tests across pre-prod and production environments. 
    • Could
      • make non-progress on tests that don't rely on date-picker 
      • try overriding selector (line 9)
      • if not, try writing new date-picker interactor 
        • create new interactor in stripes-erm-testing based on date-picker from stripes-testing
        • need to address a different way to grab data-div
        • add unit test (to support JEST debugging)
        • verify in cypress 
    • Unknowns
      • how to find which element is selected?
  • Development Estimate




In QA

Feature IDIssue IDSprint Backlog?

Notes / Estimates / Actions


SI-12 - Getting issue details... STATUS

  • Current State
  • TODO
    • Filter the input by whitelist
      • In widget type form component
      • Use as field validator, employed from a reusable utils file in dashboard
    • Add URI encoding in form submission
  • Development Estimate
    • Wed


For Elaboration

Feature IDIssue IDSprint Backlog?

Notes / Estimates / Actions

NA





For Release Prep

Feature IDIssue IDSprint Backlog?

Notes / Estimates / Actions


ERM-2506 - Getting issue details... STATUS




Bugfix Cycle

Feature IDIssue IDSprint Backlog?

Notes / Estimates / Actions








Sprint Summary

ERM

Key Summary T Assignee Status Component/s
Loading...
Refresh


Dashboard

Key Summary T Assignee Status Component/s
Loading...
Refresh

Other

Key Summary T Assignee Status Component/s Labels
Loading...
Refresh

No Label

Key Summary T Assignee Status Component/s
Loading...
Refresh