FOLIO Q2 2019 Weekly Status Report


Suggest ideas for FOLIO reports and dashboards here

See the Q2 2019 Dashboard and the Chalmers Release Dashboard in JIRA for more charts and click-through to feature details.

See /wiki/spaces/DQA/pages/2654395 for bi-weekly updates on software quality.

Weekly Updates

Report Date

Overall Status Update

Q2 Feature Count on Report Date



Functional

NFR

2019-07-02

Cate Boerema (Deactivated)

Getting issues...

Getting issues...

Click to view status update history

Q2 2019 Release Features (Functional) by Status

Getting issues...

The Jira server didn't understand your search query. If you entered JQL, please ensure that it's correctly formed. If you entered an issue key, ensure that it exists and you have permission to view it.

Q2 2019 Release Features (NFR) by Status

Getting issues...

The Jira server didn't understand your search query. If you entered JQL, please ensure that it's correctly formed. If you entered an issue key, ensure that it exists and you have permission to view it.

Status

Definition

Open 

Feature is waiting to be picked up by PO.  

Draft 

Feature is  being worked on by the PO.  Discussions are happening with the SIGs and sub-groups, mock-ups are being created.  Analysis is underway.

Analysis Complete

PO analysis is complete.  Stories are written and mockups have been created.

In Progress

Analysis is complete and development is underway.  While it is often the case that we begin development on some aspects of a feature before the PO’s analysis work has been completed, please do not move a feature into Development (In Progress) until after Analysis is Complete.  This is important so we can maintain visibility into what features that have remaining PO work.

In Review

Most or all stories in the feature are In Review (being tested).

Closed

All stories in the feature have passed test and are closed.  Feature is complete.

Product Owner Updates


DateProduct OwnerNotable Risks, Issues and/or Changes
2019-06-25
2019-06-14
2019-06-10Remaining stories from UXPROD-1377 (job profiles), UXPROD-1378 (match profiles) split and moved to a new feature UXPROD-1769 for Q3
2019-06-10Ann-Marie Breaux (Deactivated)UXPROD-1595 (connecting MARCcat and SRS) moved to Q3 2019, when MARCcat will be available for SRS to connect to. This was a stretch goal for Folijet anyway.
2019-06-10UXPROD-1768 created as a placeholder for Q3 Technical/NFR work for Data Import. Un-closed Q2 stories moved from UXPROD-1657 to it.
2019-05-28UXPROD-1604 is moved from Q2 2019 to Q3 2019 due to Chalmers changed prioritization - from Go live requirement to Can wait - up to a quarter after go-live

Click to view product owner update history

Chalmers 

One focus of Q2 2019 is delivering the features required by Chalmers to go live.  For this reason, we will take a closer look at those features in this portion of the report.  See the Chalmers Release Dashboard in JIRA for these and more click-through reports.


NOTE: There are also  Getting issues...  (UXPROD features) that have not yet been ranked by Chalmers.  As these features are ranked, we should expect the features needed below to increase.


Remaining Features Needed by Chalmers to Go-Live 

Unable to render Jira chart macro due to an execution error.

Chalmers for Go-Live Feature With No PO

key summary fixversions epic link
Loading...
Refresh

Features Needed by Chalmers for Go-Live

The Jira server didn't understand your search query. If you entered JQL, please ensure that it's correctly formed. If you entered an issue key, ensure that it exists and you have permission to view it.



Q2 2019 Release History

MetricDescription
Current featuresFeatures targeted for Q2 release as of today
  • Getting issues... Functional
  • Getting issues... NFR
Baseline release features

Baseline features targeted at beginning of quarter (April 8, 2019)

  • Getting issues... Functional
  • Getting issues... NFR